17 AC Total Sitework providing infrastructure for future commercial development. Project included Erosion, Clearing, 134,000 CY Excavation, 2,300’ Sanitary, 2,900' Storm, 4,400' Water 45,000 SF Site Concrete, 13,000 TN Stone Base, 4,500 TN Asphalt and Restoration.