Vint Hill Public Street Network– Phase I

We were excited to work on the former Army and NSA base near Warrenton to demo 45,000 SY of outdated roadways and parking lots and build new infrastructure including 9,800 LF of roadway. The project had 60,000 CY of excavation; over 4 miles of water, sanitary and storm pipe; 18,000 LF of curbs; over 14,000 tons of CTA and 11,000 tons of asphalt paving. Sidewalks and trails were welcome amenities for local users. A groovy roundabout improved traffic flow and this new roadway network improves connectivity for the public and planned future growth.